HRIBF Newsletter, Edition 17, No. 2, Aug. 2009 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Feature Articles
Regular Articles 1. HRIBF Update and Near-Term Schedule
In the last two editions of the Newsletter, the HRIBF Update dealt primarily with the July 2008 Operational Emergency (OE) and its aftermath. If you are not familiar with the OE, I encourage you to have a look at the HRIBF Update in the February 2009 Newsletter, since I will make reference to events, committees and reviews in this article without providing full background information. I am pleased to report that this Update will have a more optimistic tone than the last two. There have been many positive developments in the December 2008 through June 2009 period. First and most important, we have completed some excellent science with long-lived radioactive ion beams (7,10Be and 26Al) operating in "batch mode". Other important accomplishments included completion of the required corrective actions which were developed based on the Management Investigation Team report, and completion of the Triennial Review of the HRIBF by the ORNL Accelerator Safety Review Committee. We have now completed the phased restart plan discussed in the February 2009 Newsletter and obtained permission for full operation of the HRIBF. In addition, excellent progress has been made on the IRIS2 project, including completion of the Accelerator Readiness Review (see the Update on IRIS2 in this newsletter), which will be fully operational before the end of calendar year (CY) 2009. In spite of an extended Continuing Resolution to start FY2009, HRIBF is in better fiscal shape than it has been in many years. We actually may be able to make much-needed additions to the facility staff as part of a long-standing, but much delayed, facility staffing plan. The President's Request for fiscal year (FY) 2010 also looks very encouraging, though the congressional marks are less so. Restart of an accelerator facility after an extended shutdown (almost a year in this case) is seldom easy. ORIC has always been vulnerable to the effects of such shutdowns, and this case has been no exception. We have experienced several intermittent failures during the initial weeks of operation. We are systematically working through these problems to ensure successful RIB campaigns. We have obtained $2.5M of American Recovery and Reinvestment Act (ARRA/stimulus) funds which will be applied to the refurbishment of ORIC systems over the next four years. Our current plan is to complete the ongoing fluorine campaign in the fourth quarter of FY2009, and move to an extended neutron-rich campaign which will continue well into CY2010. This campaign will be the first to take advantage of a completed and fully commissioned IRIS2.
This has been very difficult and frustrating year. The HRIBF
operations staff deserves high praise for the way they maintained
morale and for the work they accomplished. Of course we realize that
it has also been a terribly frustrating time for our users as well.
We are determined to recover quickly from the restart issues, and to
provide a much improved level of facility operation with IRIS2 on line
and with new investments in ORIC beginning to have an impact
(see my
article on HRIBF driver upgrade in the February Newsletter).
2. Recent HRIBF Research -
Measurement of
the 26Al(d,p)27Al
Reaction for the Study of the Astrophysical 26
Al(p,
γ)27Si Rate
Astronomical gamma-ray mapping, by charting the distribution of specific isotopes, yields information which can constrain the rate of explosive nucleosynthesis events (such as novae and supernovae) within the galaxy. One of the landmarks in observational astronomy has been the detailed galactic mapping of the decay of 26Al, achieved by the observation of the 1809-keV gamma rays emitted following its beta decay using the COMPTEL instrument aboard the Compton Gamma Ray Observatory (see Fig.2-1), and more recently the European Space Agency's INTEGRAL satellite. With a half-life of ~105 years, the distribution of 26Al provides an insight into the galactic nucleosynthesis over a timescale of about the last million years. The mechanisms contributing to the formation and destruction of 26Al are consequently of direct interest to the interpretation of these gamma-ray maps [2].
In most astrophysical environments, 26Al is destroyed via the 26Al(p,γ)27Si reaction. Understanding states near the proton threshold in 27Si is crucial for constraining this reaction rate, and thus for elucidating the amount of 26Al which survives to enrich the interstellar medium. The difficulty in measuring directly the strengths of these resonances, due to their small cross sections, means that indirect approaches are required. Furthermore, due to the difficulties inherent in measuring proton transfer reactions, an alternative is to measure mirror states in 27Al to obtain information about the 27Si structure. The 26Al(d,p)27Al reaction has been measured in inverse kinematics at the HRIBF, in order to study states in 27Al which are mirror to those in 27Si. A batch-mode beam of 26Al, of typically 5 million particles per second, impinged on a ~150 mg/cm2 CD2 target for ~5 days. Proton ejectiles were detected in the SIDAR and ORRUBA silicon detector arrays, subtending angles from ~90-165 degrees in the laboratory frame. These data represent the first measurement performed with a complete barrel of ORRUBA. Elastic scattering was monitored in ORRUBA detectors mounted at angles just forward of θlab = 90°. A forward array for recoil tagging, comprised of annular segmented silicon detectors of Micron QQQ2 design, covering angles from ~1.5 to 10 degrees, was used to detect 27Al ions coincident with (d,p) protons.
Figure 2-2 shows an online spectrum from a single strip of SIDAR, for a
subset of the data taken during the experiment. Transitions at these
backward angles are strong candidates for ℓ = 0 transfer, pending a
full analysis of angular distributions. These data are under analysis
by, and will contribute to the PhD thesis of Stephanie Brien from the
University of the West of Scotland.
Figure 2-2: Proton energy spectrum from the 26Al(d,p)27Al reaction, for a single SIDAR strip, for a subset of the data.
References:
[1] S. Pluschke et al., "The COMPTEL 1.809 MeV Survey" in Proceedings of the 4th INTEGRAL Workshop, A. Gimenez, V. Reglero, and C. Winkler, eds. (ESA Publications, Noordwijk, 2001). 3. Recent HRIBF Research -
Study of the Elastic and Inelastic 26Al+p Reactions at HRIBF
The detection of characteristic gamma-rays from the decay of 26Al
(t1/2=7.2x105 yr) has provided clear evidence of continuing
nucleosynthesis in the Milky Way Galaxy. Detailed maps of Galactic
26Al have been made by satellite gamma-ray observatories such as
COMPTEL [1], RHESSI [2], and INTEGRAL [3]. The observed 26Al was
concentrated along the Galactic plane, but the source is still not
known. Possible sources include Wolf-Rayet stars, novae, and
core-collapse supernovae. Peak temperatures in these environments
vary from 0.03 to ~3 GK meaning that relevant reaction rates need to
be known over a broad temperature range to estimate the contributions
of these events to the Galactic 26Al abundance.
Figure 3-1: The experimental
configuration used in the 26Al(p,p)26Al measurement.
Of the relevant reactions, the 26Al(p, γ)27Si reaction is thought to
provide the dominant destruction mechanism over a large temperature
range. Levels in 27Si above the proton threshold at 7.463 MeV provide
possible resonances in the 26Al(p, γ)27Si reaction. While there have
been many studies of this reaction [4-7], there are many levels in the
relevant energy range (Ex=7.5-8.5 MeV) for which their spins and
proton-widths are not known. Also important to know is whether the
effective lifetime of 26Al is changed in the high-temperature stellar
environment as a result of inelastic excitations. While the 5+ ground
state has nearly a million-year half life, the 0+ metastable state
only lives 6.3 s. If there are 27Si levels through which 26Al could
inelastically-scatter into the metastable state, the effective half
life of 26Al could be greatly reduced.
To address these uncertainties, we have measured the elastic and
inelastic 26Al+p scattering reactions at HRIBF. Pure 26Al beams with
intensities of 2x106 26Al/s were used to bombard
50 μg/cm2 CH2 targets
(see Fig. 3-1). Scattered protons were detected in the angular range
18-41 degrees by the SIDAR Silicon Detector Array [8]. The recoil
26Al ions were detected in coincidence with the protons in an
isobutane-filled ionization counter. The unscattered primary beam was
prevented from entering the ionization counter by a 1-cm-diameter disk
that was inserted in front of the counter entrance window during each
run. The size of the disk was chosen so that for the proton angles
covered by the SIDAR, the corresponding recoil 26Al ions were not
blocked by the disk. The energy spectrum detected in SIDAR is shown
in Fig. 3-2 in singles and coincidence demonstrating the cleanliness of
the proton identification in the coincidence data. The proton yields
were measured at 45 energies from Ec.m.=0.5-1.5 MeV over a period of 7
days in March 2009. The data are currently under analysis and will
constitute the Ph.D. thesis of University of Tennessee graduate
student Stephen Pittman.
Figure 3-2: The energy spectrum
observed at 27 degrees for a 15-MeV 26Al beam bombarding a 50 μg/cm2
CH2 target in singles and in coincidence with a recoil 26Al ion.
References:
[1]R. Diehl et al., Astron. Astrophys. 298, 445 (1995). 4. Recent HRIBF Research - Resonant
Scattering of 10Be on 4He
The structure of the beryllium isotopes is rather unusual, but
highlights the spectrum of possible structural characteristics of
light nuclei. The nucleus
8Be is well-known to posses a structure
which can be described in terms of two alpha-particle clusters. From
an experimental perspective the ground state rotational band may be
described by a moment of inertia commensurate with two touching
alpha-particles. Such a structure is also found in the Greens Function
Monte Carlo calculations [1] in which no cluster structure is apriori
assumed. The addition of neutrons to the 8Be nucleus to form isotopes
such as 9,10Be produces some rather interesting
characteristics. Rather than destroying the symmetries responsible for
the clustering in 8Be, the two alpha-particle cluster structure
remains and the valence neutrons are exchanged between the two
alpha-particle cores in a covalent, molecular, manner [2]. The
orbitals of the neutrons have either σ or π character, just as
electrons exchanged in atomic molecules. The nature of the bonds
depends on the orientation of the p-orbitals which are occupied by the
neutrons at each alpha-particle centre. When the orbitals are aligned
perpendicular to the separation axis then π-bonding results, whereas
if the alignment is parallel the bonding is of σ-character (see
Fig. 4-1) [2].
Figure 4-1: The formation of the molecular orbitals from the linear combination of p-orbitals built around two alpha particles.
In the ground-state of 10Be the two neutrons, asymptotically, have
π-behaviour. Such systems are nuclear dimers. The question then arises
as to if it is possible to form trimers, i.e. three-alpha-particles
and valance neutrons. From a theoretical perspective the answer
appears to be yes, though the precise geometric arrangement of the
alpha-particles is unclear (linear or triangular) [3,4]. The
experimental situation is a little more unclear. Reference [5]
summarises the latest situation. A great number of resonant states
have been observed that exist above the alpha-decay threshold (12
MeV), but their spins are largely unknown and this prevents any
systematics being determined.
The present study was of resonances in 14C populated in the 10Be+4He
resonant scattering reaction. The 10Be beam used had an intensity of
~107 pps and the contamination from 10B was ~1%. Nine beam energies
ranging from 25 to 46 MeV were used to perform the measurements. The
experimental arrangement is shown schematically in Fig. 4-2. The SIDA
chamber was positioned in front of the Daresbury Recoil Separator and
was sealed with respect to the beam line with a 5 μm thick havar
window. Helium gas was held at a pressure of 900 mb.
Figure 4-2: The arrangement of the two LAMP configurations used to
coincidently detect the 10Be and 4He
products. The detectors were placed within the gas volume.
Within the gas volume were a number of silicon detectors. At zero
degrees a three-element silicon telescope formed from three, 150-μm thick
detectors was screened from the beam by mylar foils. These foils
allowed the resonantly scattered alpha particles to pass through to
the telescope behind. This provided a measurement of the zero-degree
yield for the alpha-particles. In addition two LAMP arrays of YY1 type
silicon detectors (Micron Semiconductors Ltd) were located within the
helium gas volume. These were used to detect the 4He+10Be nuclei in
coincidence as illustrated in Fig. 4-2. These detectors allowed the
elastic and inelastic channels to be identified, the angular
distributions of the reaction products to be calculated, and finally
the location (distance from the window) of the inte raction to be
calculated. The data from these latter detectors permit the angular
distributions of the resonances observed in the zero-degree detector
to be calculated and thus the resonance spins to be deduced. The
zero-degree excitation function for the 25-MeV beam energy is shown in
Fig. 4-3 and the energy angle systematics for the 4He particles in
Fig. 4-4. The analysis of data is ongoing.
Figure 4-3: The 14C excitation energy spectrum populated
in 4He+10Be resonant scattering for the beam energy of 25 MeV.
Figure 4-4: Energy versus angle systematics (measured with respect to the chamber window) for the
two LAMP arrays for Ebeam=25 MeV.
References:
[1] R. B. Wiringa, S. C. Pieper, J. Carlson, and V. R. Pandharipande, Phys. Rev. C 62, 014001 (2000). 5. Recent HRIBF Research - Measurement of Levels in the Halo Nucleus 11Be via 10Be(d,p) in Inverse Kinematics
Phenomena such as neutron halos and level inversion make the light
neutron-rich nuclei fascinating test cases to study the evolution of
nuclear structure away from stability. 11Be is an archetypal example
of both of these effects, and is one of the heaviest nuclei for which
ab-initio theory is presently practical. Although 11Be has been
studied thoroughly via (d,p) in normal kinematics [1], β-decay[2],
breakup[3,4], and (p,d)[5] experiments, there still remains a paucity
of knowledge about the bound first-excited state, for which
spectroscopic factors are disputed, and the resonances.
We have performed a 10Be(d,p)11Be experiment in inverse kinematics
using a new batch-mode 10Be beam at the energies of
60 and 107 MeV and deuterated
polyethylene targets. The angular distribution of protons ejected in
the population of bound states and low-lying resonances in 11Be will
be used to extract spectroscopic factors for those states. The Oak
Ridge Rutgers University Barrel Array (ORRUBA) was used in conjunction
with the Silicon Detector Array (SIDAR) for a large solid angle
coverage and nearly continuous coverage in polar angle from 45° to
165° in the laboratory reference frame. The new QQQ array and Dual
MCP detectors were placed at forward angles to detect recoils and to
help discriminate between (d,p) and fusion-evaporation events. A
schematic view of the silicon detector setup is shown in Fig. 5-1.
The angular coverage is shown with expected angular distributions in
Fig. 5-2.
Figure 5-1: Silicon detector setup. The ORRUBA and SIDAR arrays were used for detection of protons from (d,p) and elastically scattered deuterons.
Figure 5-2: Angular coverage with expected angular distribution.
Coverage in polar angle was nearly continuous from 45 to 165 degrees
in the lab frame, with only a small gap due to target frame shadowing.
Preliminary analysis of the proton data in SIDAR yields excellent
statistics for the bound states and first resonance, as shown in an
ungated spectrum in Fig.5-3. The first excited state at 320 keV is
clearly separated from the ground state (two groups to the right of
the figure). Other low-lying resonances have been observed in our
preliminary analysis of the proton energy spectra from SIDAR.
On completion of calibrations both for SIDAR and ORRUBA, the full data
analysis is expected to yield angular distributions with very low
statistical uncertainties.
Figure 5-3: Energy distribution of
protons at back angles. Protons from the population of the ground
state and 0.320 MeV first-excited state are well resolved, and
tremendous statistics were recorded for the wider first resonance.
Special thanks are due to the staff at HRIBF for a very successful run, especially Dan Stracener. References:
[1] D.L. Auton, Nucl. Phys. A 157, 305-322 (1970). 6. Recent HRIBF Research - Use of 7Be Beam in Wear
Studies (Proof-of-Principle Experiment)
Currently in the United States, about 200,000 hip-joint replacement
surgeries are performed each year. Worldwide, the number is nearly 1
million [DeG04, Feh00]. Unfortunately, these implants do not last
forever, but seem to have useful lifetimes (limited by wear) between
10 and 20 years. The aim of wear studies on artificial hip joints is
to extend the lifetime of the implants through development of more
durable materials, as well as to make recommendations for the patients
on lifestyle (activity) choices.
Substantive work has been going on in the past decade to improve the
lifetime of metal-plastics joints. The wear of plastics is nearly
exclusively measured by gravimetric methods. Due to the low wear, long
test times are necessary to achieve reasonable accuracy. Also, fluid
soak from the lubrication fluids can lead to high systematic errors in
this method. We have performed a proof-of-principle experiment at the
Holifield Radioactive Ion Beam Facility (HRIBF) to show the principal
viability of a radiotracer method based on uniformly implanted 7Be for
wear analysis.
The radioactive 7Be for the experiment was obtained from the ATOMKI
cyclotron institute in Debrecen, Hungary, where it had been produced
via the 7Li(p,n)7Be reaction.
After chemical extraction from the 7Li
matrix at HRIBF, the 7Be matrial was transferred to a sputter cathode for
injection in the HRIBF tandem accelerator. A new 7Be implantation
setup had been developed at the Colorado School of Mines and was
installed at a free beam line at HRIBF (Fig. 6-1). The activity
available resulted in 7Be-beam currents of
105-106 ions per second at
the sample location.
Figure 6-1: 7Be implantation setup
during beam time at HRIBF.
The 8-MeV energy of the beam was transformed into a broad energy
distribution (measured with a silicon detector in the implantation
position) using a wheel of 20 foils (increasing thickness from zero to
10 μm in 0.5 μm increments) and additional energy "smearing"
foils. Based on the foil thicknesses an activity plateau (with depth)
in the polyethylene from 0 to approximately 9μm was achieved on which wear
studies were subsequently performed. Total 7Be implantation doses
varied from 109 to 1010 nuclei on the 7 pins used.
For artificial hip joints with metal-plastic couplings, a typical wear
range lies between 0.1-1 mg/(cm2*1 million motion cycles). This
corresponds to a depth wear of about 1.08-10.8μm per 1 million
motion cycles. Motion simulators work at a speed of about 1 Hz, giving
a time of about 2 weeks for one million cycles, well matched to the
7Be half-life. The wear studies were performed with a specifically
designed motion simulator supplied and operated by Rush University
Medical Center in Chicago. The Pin-on-disk (POD) design replicates the
motion trajectories of artificial joints. For this experiment 2 types
of plastic materials were available: One conventional high-density
polyethylene, the other cross-linked high-density polyethylene. The
latter material had been advertised as significantly superior to the
previously used conventional materials. However, due to the lower wear
and the problems of the gravimetric method with fluid soak a direct
quantitative comparison had not been possible.
Figure 6-2: Pin-on-disk orthopedic
wear testing system.
The wear studies were performed at Argonne National Laboratory and
used a 20% Germanium detector setup for 7Be gamma detection. The
plastic pins underwent a known number of wear cycles in the POD system
(lubricated with bovine serum) before being cleaned and transferred
for activity measurement. The results of the complete wear experiment
(extending over 4 months) are depicted in Fig. 6-3. Shown in the figure is the
fraction of activity worn off (natural decay corrected) as a function
of wear cycles. Clearly visible is the different behavior of
cross-linked (the rising group of 4 samples) and conventional material (the relatively flat group of 3 samples) with a
preliminary result of a wear ratio of app. 13 (40.6%/106 cycles
conventional; 3.1%/106 cycles cross-linked). Error analysis and
further simulations of implantation depth are still ongoing.
Figure 6-3: Cumulative 7Be activity
wear loss as a function of wear cycles.
This proof-of-principle experiment shows the usefulness
and practical potential of the use of 7Be implantion as a radiotracer
for wear studies. Further analysis and experiments have to look at
improvements in the activity measurements (to reduce scatter and
systematical error), the influence of radiation dose on mechanical
properties (will provide upper limits on allowable 7Be implantation
dose) and the possibilities of extending the method to natural
materials.
The experiment was performed as a collaboration between the Colorado
School of Mines (U. Greife, L. Erikson, N. Patel), Rush University
Hospital (M. Wimmer, Y. Dwiwedi, M. Laurent), Oak Ridge National
Laboratory [K. Chipps (Rutgers), D. Bardayan, J. Blackmon (LSU),
C. Gross, D. Stracener, M. Smith, C. Nesaraja, R. Kozub (TTU)] and
Argonne National Laboratory (E. Rehm, I. Ahmad)).
References:
[DeG04] J. DeGaspari, Mech. Eng. 12 (2004) 7. Update on Injector for
Radioactive Ion Species 2 (IRIS2)
The IRIS2 Project will be completed this Fall. Suspension of HRIBF
operations following the July 2008 Operational Emergency had a
positive impact on the project for several months relative to
installation activities, but the resumption of operations and required
Authorization Basis documentation updates have slowed down some of the
commissioning activities. Nevertheless, substantial progress has been
made.
Installation of most equipment is complete. The injector and
transport beamlines are fully assembled, tested, and operational. This
includes the transport beamline 35 degree and 90 degree electrostatic
deflectors.
The modular laser room has been installed, and drilling of the 8-inch
diameter hole for the laser and utility port plug through the
9.5-foot-thick concrete shielding wall has been completed. Laser
safety system procurement is underway, and a segmented polyethylene
plug with three laser beam conduits and two utility conduits is in
fabrication.
Iron storage boxes for storing activated target ion sources have been
received, as well as the contamination control boxes. The activated
target ion source storage area outside of the target room has been
constructed. This is a concrete wall storage compartment that will
accommodate up to six of the iron boxes. A below the hook lifting
fixture for manipulating the boxes with the existing 12.5 ton bridge
crane has been tested and approved for use. Testing and programming
of the target room crane is in progress in preparation for
commissioning. Pick-up and set-down points within the room are being
finalized.
The Operational Readiness Review was not received as early as
expected, but most findings have been addressed with the primary
exception being the completion of revisions to the HRIBF Safety
Assessment Document (SAD) and the Accelerator Safety Envelope (ASE).
Although the revisions that are specific to IRIS2 are straightforward,
other revisions that are associated with our July 2008 Operational
Emergency are more complex. We are in the process of incorporating
Accelerator Safety Review Committee (ASRC) comments on our draft
revisions and expect these documents to be approved in early
September. This delay has not impacted IRIS2 stable ion beam
commissioning, but RIB commissioning cannot begin until the updated
SAD and ASE are approved.
Stable ion beam commissioning has proceeded quite well. Beam has been
transported from the target ion source through the injector and
transport beamlines into beamline 12, the existing isobar separator
beamline. The 1st-stage mass separator has been optimized for maximum
mass resolution. Mass separation of 131Xe and
132Xe has been
demonstrated, with a measured resolving power of m/Δm = 1250 (error
bars of +/-30), as shown in Figure 7-1, and we continue to optimize beam
optics components and transmission.
Figure 7-1: Screen capture of the Beam Profile Monitor (BPM) display
showing the horizontal profiles of the separated isotopic beams of Xe
at the image position of the separator magnet system. Units are
arbitrary.
8. PAC-15 Results and PAC-16
PAC-15 met July 22-23, 2009, in Oak Ridge and considered 26 proposals
and letters of intent which requested
371 shifts of radioactive beams (RIBs),
12 shifts of in-flight RIBs,
77 shifts of low intensity stable beams (SIB for RIBs), and
65 shifts of stable beams (SIBs).
Of these, a total of
212 RIB shifts (57 long-lived isotopes),
6 in-flight RIB shifts,
63 SIB for RIB shifts, and
12 SIB shifts were approved.
Proposals accepted
by HRIBF requested RIBs of
7,10Be,
17,18F,
59Fe,
56Ni,
73,74,77Cu,
81,82Zn,
83Ga,
85As,
130,132Sn, and
132Te.
The total number of accepted proposals was 17; 13 of which were from
outside organizations.
Ray Kozub, chair of the Users Executive Committee,
represented the Users at the meeting.
Alan Shotter's tenure on the HRIBF PAC has come to an end with PAC-15
and the facility thanks him for his service. He will be replaced by
Jens Dilling of TRIUMF.
We anticipate PAC-16 to occur in late spring
2010.
9. Improvements to User
Access and Possible Future Changes
ORNL is attempting to improve user access to HRIBF and other ORNL User
Facilities. Intermittent visitors, ie. most users, will begin
receiving a "user entry pass" via email 7 days before arrival
and
completion of ORNL's Site Access Training (SAT). This pass will
contain relevant information including the start date as well as
contact information in case problems arise. A bar code will also be
included which the guard at the portal will scan. It is anticipated
that this will shorten the time spent at the portal.
The user entry pass is optional; it is not required for entry so don't
panic if it is lost or damaged. Our hope is that time spent with the
guards at the portal will be minimized. Remember that proper photo ID is
still required at the checkpoint, and foreign nationals will still
need to present their passport and visa at the Visitor Center.
There is also a draft DOE order 142.3 pertaining to Unclassified
Foreign Visits and Assignments. We are working with
National User
Facility Organization and others to provide comments and suggestions
for improving the order. If these efforts are successful, we
anticipate more improvements regarding HRIBF access to users in the
future.
10. HRIBF, Upgrade for the Era of FRIB - A Users Workshop Will be Held on November 13-14, 2009
The science of rare isotopes is blooming worldwide. With the
FRIB on its way, the time has come for the HRIBF to better define
itself in a new era. Now, as we have learned about the scope of the
FRIB, we are in an excellent position to assess the unique scientific
opportunities provided by the intense ISOL beams of the HRIBF for
nuclear structure and reactions, nuclear astrophysics, and
applications of nuclear science, and to thereby promote the
complementary features the HRIBF has with the FRIB and other RIB
facilities.
To this end, the HRIBF Users Executive Committee is calling a
workshop, HRIBF, Upgrade for the Era of FRIB,
on Friday and Saturday, November 13-14, 2009, at the Pollard
Auditorium in Oak Ridge to inform the user community about a proposed
new cyclotron driver to replace the ORIC (click here for a
description). The primary goal of the workshop will be to develop a
user-driven white paper that will contain a science case for a modern,
reliable ISOL facility at ORNL. This workshop will also offer an
opportunity to attract new users, especially in the context of the
envisioned future GRETINA campaign at the HRIBF.
There will be introductory talks on Friday morning about the
FRIB and various ISOL facilities. This will be followed on Friday
afternoon and evening by parallel discussion sessions in working
groups on nuclear structure (in-beam and decay), reactions,
applications, astrophysics, and ISOL technology. The discussions
should focus on the scientific strengths of HRIBF in the future FRIB
era and on the research that can be done in support of FRIB science.
The proposed HRIBF upgrade would result in new isotopic beams and an
increase in RIB intensity, so new equipment necessary to take
advantage of these improvements should also be covered in the
discussions. The format of these break-out sessions is expected to be
characterized primarily by detailed round table discussions built
around the topics specified by the conveners, with few if any formal
presentations. The conveners of these groups are being recruited from
the user community, and they will be responsible for writing their
respective sections of the white paper. In addition to the areas
mentioned above, the final document will also include sections on the
complementarity of FRIB-HRIBF science, FRIB-HRIBF instrumentation, the
worldwide context of the proposed upgrade, education and outreach, and
the relation to nuclear theory. Working groups will summarize their
findings on Saturday morning.
More details about the HRIBF Users Workshop can be found at its website,
which will be updated frequently in coming weeks and months. Meanwhile, if you have questions or suggestions
concerning this workshop, please contact us. Your active participation
is very important to the future of the HRIBF and its niche of ISOL/RIB
physics in the U.S. We hope to see you there!
Regular Articles RA1. RIB Development
The RIB development group has been involved in several efforts at the
On-Line Test Facility (OLTF) and at the High-Power Target Laboratory
(HPTL) to develop new radioactive ion beams and to improve the quality
of the beams that are currently available at the HRIBF.
A group led by Jon Batchelder (ORAU) has made several on-line tests to
optimize a target and ion source for the production of 97Ag beams.
The search for an isomer in 97Ag is a PAC-approved experiment. The
97Ag nuclei will be produced in the reaction of a 54Fe beam with an
enriched 50Cr target. These tests have included measurements of
silver holdup times using different materials for the target holder
and catcher foil, including molybdenum, tantalum, graphite, and
niobium.
Another project, led by Ron Goans (a student from University of Tennessee),
is seeking to
understand the differences in yields of neutron-rich tin and germanium
isotopes from uranium carbide targets that are produced using various
techniques. Our data from the IRIS1 injector indicate that the RIB
intensities of neutron-rich Ge and Sn isotopes are higher when UC/RVC
targets are used than the intensities observed when we are using
targets fabricated from UC powders. The UC/RVC targets are produced
by coating a low-density, highly-porous graphite matrix with a layer
of uranium carbide, resulting in a target density of about 1 g/cm3.
We have not used these targets lately since the fabrication process is
complex and it has been difficult to consistently produce high-quality
targets. Over the last couple of years, we have used targets produced
by pressing a mixture of UC powder with graphite powder. These
targets, with densities of about 2.2 g/cm3, have performed quite well
in terms of longevity and RIB yields with the exception of Ge and Sn
isotopes. Beams of these two elements are purified by extracting
positively charged sulfide molecules of these elements. Sulfur is
added to the system via the introduction of hydrogen sulfide. Ron is
investigating different methods of introducing sulfur into the system
and looking at differences in the holdup times of the elemental ions
and the molecular ions as a function of target material, target
temperature, and sulfur concentration.
Another student, Cara Jost (Mainz), is continuing her investigation of
a technique to purify neutron-rich strontium beams by selectively
trapping the rubidium contaminants on surfaces in the transfer line
between the UC target and the ion source. It is known that Group I
elements can be trapped on a quartz surface at relatively high
temperatures (up to 1200° C). Cara has measured holdup times of
several elements (both stable and radioactive) at different
temperatures for a variety of materials (quartz, sapphire, tantalum)
and geometries, including "straight-thru" tubes and "blocked" tubes
where the average number of interactions with the wall is much higher.
At the HPTL, we have recently completed an on-line measurement using a
proton beam from ORIC to irradiate a niobium silicide target for the
production of 25Al and 26Al.
The normalized yields were lower than we
had previously measured from a SiC fiber target. This is partly
explained by the high density (4.2 g/cm3) and low porosity of the
niobium silicide targets. We will produce another set of niobium
silicide targets that are more suitable for the release of short-lived
isotopes. Further investigations are needed to determine the best
targets for these aluminum beams. To this end, we have purchased a
couple square meters of silicon carbide cloth woven from fibers with a
nominal diameter of 10 microns. These materials are certified to have
very low oxygen content, which is important since silicon oxides are
quite volatile at the HRIBF ion source operating temperatures.
RA2. Accelerator System Status
ORIC Operations and Development (B. A. Tatum)
Due to the July 2008 Operational Emergency, ORIC remained shut down
for most of the January--to-July period as various corrective actions were
implemented. As part of the phased restart of the facility, we
received permission in late winter to deliver light ion beam to
non-uranium targets at the High Power Target Laboratory (HPTL). A
nominal 54-MeV proton beam was subsequently delivered to a niobium
silicide target at the HPTL for the production of
25Al and 26Al beams.
Details of this beam development activity are provided in this Newsletter
by Dan
Stracener on RIB Development.
Permission to resume full facility operations including proton beam on
uranium carbide targets was granted in late June following the
completion of all necessary corrective actions related to the
Operational Emergency. As mentioned by Jim Beene in his
HRIBF
Update and Near-Term Schedule, starting ORIC after many months of
shutdown is difficult. We have been systematically restoring the
machine to an operational status and have had a few setbacks along the
way. Examples of difficulties include mechanical drive system vacuum
seals which become rigid when not exercised, and current power
supplies that have not operated at high current levels for an extended
period. Nevertheless, we are anticipating a resumption of routine
operation for the proton- and neutron-rich experimental programs
during the remainder of the summer and into the fall.
We have been awarded $2.5M in American Recovery and Reinvestment Act
(ARRA/stimulus) funds to be utilized over the next four years. One of
the major uses of these funds will be the replacement of the
1938-vintage ORIC main magnetic field motor-generator set which
provides up to 5000Adc at 360V to the main magnet coils. The MG set
will be replaced with a dc power supply. The present plan is to
retain the MG set as a backup. Improvements will also be made to the
ORIC extraction and rf systems, the 1960's vintage diffusion pumps
will be replaced, high-current beam stops will be installed, HVAC
stack monitors will be implemented, and the IRIS1 target handling
system electronics will be upgraded. These improvements combined with
base capital equipment and Accelerator Improvement Project funds will
substantially modernize ORIC and lead to higher reliability.
RIB Injector Operations and Development (P.E. Mueller)
During the period from January 1, 2009 to June 30, 2009, the 25 MV
Tandem Electrostatic Accelerator delivered beams of
Other beams of 26gAl from 13 to 40 MeV were also delivered to
Beam Line 41.
All of these beams were produced with the multisample cesium sputter negative
ion source using pressed powder copper targets loaded with
26gAl2O3, 7BeO, or 10BeO
as appropriate.
Tandem Operations and Development (M. Meigs)
The Tandem Accelerator was operated for more than 1900 hours since the
last report. The machine ran at terminal potentials of 1.34 to 24.65
MV. The multi-sample ion source was used on IRIS1 to provide the
radioactive beams of 7,10Be and 26Al.
In addition, the SNICS was used
to provide the stable beams 1H, 7Li, 17,18O,
27Al, 54Fe, 58Ni, 76Ge,
107Ag, 115In, and 120Sn. About
64 hours were spent conditioning, most
of which was necessary after a spark at 24.65 MV caused
deconditioning. Three tank openings were completed during this
period; the first to repair the foil stripper which had stuck in
place, the second to do regular maintenance and to repair the low
intensity diagnostics in preparation for radioactive beams, and the
last to repair the gas stripper. Quite a few hours during this period
were spent on SNICS development, leading to a greater understanding of
the operation of the source.
RA3. Experimental Equipment - The Oak Ridge Isomer Spectrometer and Separator (ORISS)
In 2003, the UNIRIB Consortium set out to develop a universal means
for providing high-purity radioactive beams for nuclear decay
spectroscopy. High intensity backgrounds of adjacent nuclei are the
principal impediment in many decay studies of such exotic nuclei. Many
techniques exist for purifying RIBS, including laser ionization,
molecular sideband, ranging out and others. Magnetic isobar separators
are also frequently used.
The method chosen by UNIRIB was an electrostatic longitudinally
dispersive separator based on the multi-turn time-of-flight technique
[Cas01, Ish04]. The UNIRIB goal was initially a mass resolution of
15,000 as a separator. The technique was universal, applying equally
well to all elements, and the goal of 15,000, which was beyond
anything achieved at that time, is sufficient to significantly reduce
other members of the mass chain.
Since that time the UNIRIB Consortium has advanced three separate
technologies which when combined into one instrument will far exceed
the original goal of a mass resolution of 15,000. Our instrument,
ORISS, will consist of three components:
Using funding from a recent DOE grant, the assembly and remaining
construction will be completed. Off-line tests of ORISS should be
performed within one year. ORISS will be initially commissioned and
used for experiments at the online isotope separator, UNISOR, in
2011. A picture of the existing time-of-flight spectrometer is shown
in Fig. RA3-1. A draft of the layout for ORISS at UNISOR is shown in
Fig. RA3-2.
Figure RA3-1: View of the main component of ORISS, the multi-turn
time-of-flight mass spectrometer in its vacuum chamber.
Figure RA3-2: Conceptual layout of ORISS at the UNISOR on-line test
facility, where commissioning and first experiments will take place.
Experimentally determined performance data from the RFQ, the
time-of-flight spectrometer, and the Bradbury-Nielsen gate together
with calculations from an ion optics code we developed [Shc05] allowed
us to predict the performance of ORISS when completed. We expect to
obtain:
ORISS will provide pure beams of any isobar thus satisfying the
original goal. However, the significantly improved performance of
400,000 provides a "quantum leap" in capabilities for decay
spectroscopy by adding the ability to produce pure beams of isomers
with a relative mass difference M/ΔM < 200,000 (corresponding to an
excitation energy of an isomeric state > 470 keV in a mass A = 100
nucleus). For isomeric states with relative mass differences M/ΔM >
200,000, ORISS will be able to produce enriched beams. ORISS will
provide unparalleled capabilities for nuclear structure experiments
such as:
In order to demonstrate the power of ORISS, we show in Fig. RA3-3 a
simulated time-of-flight spectrum with a mass resolving power
full-width at half-maximum of ~ 400,000 for the mass A = 77 isobaric
chain. The full width at half-maximum of the time-of-flight peaks is
14 ns. All isobars and the 772-keV isomer in 77Zn are clearly resolved
in the spectrum. Pure beams of these nuclides can be produced using
the Bradbury Nielsen time gate which can be switched from "open" to
"closed" within 10 - 15 ns. The gate will be opened for ~30 ns when
the desired nuclide arrives at the gate, and this nuclide will be
transmitted to a detector station located further down-beam. All other
nuclides arrive at the gate when it is closed, and they will be
laterally deflected into a beam dump area. The isomeric state in 77Ge
with an energy 160 keV would not be resolved in the time-of-flight
spectrum but could be identified since the resulting sum peak of 77mGe
and 77Ge (ground state) has a larger width (20 ns) than the ground-state peak alone (14 ns).
Figure RA3-3: Simulated time-of-flight spectrum for A = 77 isobars in
ORISS after 300 laps, a time-of-flight of 16 ms. Energy differences
[MeV] relative to 77Se (ground state) are indicated. The mass
resolving power amounts to 430,000 full-width at half-maximum.
References:
[Bra36] Absolute Values of the Electron Mobility in Hydrogen,
N.E. Bradbury and R.A.Nielsen, Phys. Rev. 49 (1936) 388. RA4. Users Group News
The HRIBF will hold its annual Users Group Meeting in Oak Ridge this year.
The meeting is planned for November 13-14, 2009; more details may be
found in Feature article 10 of this newsletter.
This expanded Users Group meeting is expected to become an annual event
which may supplant the usual meetings carried out at the annual fall
DNP meetings.
The previous meetings, held jointly with ATLAS, NSCL, GAMMASPHERE/GRETINA,
and RIA Users groups, will most likely be reformatted now that we are
in the FRIB era.
At this year's DNP, it is expected that there will
be a short informational-type presentation.
More details will be provided by email.
One targeted user workshop will be held November 12, 2009, immediately
before the annual meeting. The workshop will be on science
applications and cross-disciplinary fields at HRIBF. It is hoped that
this workshop will be held at the
same location (Pollard Auditorium on the ORAU campus) although there
may be a conflict.
Users should contact
Alfredo Galindo-Uribarri
for more information.
RA5. Suggestions Welcome for New Beam Development
HRIBF welcomes suggestions for future radioactive beam development. Such
suggestions may take the form of a Letter of Intent or an e-mail to the
Liaison Officer at
grosscj@ornl.gov.
In any case, a brief description of the physics to be addressed with
the proposed beam should be included. Of course, any ideas on specific
target material, production rates, and/or the chemistry involved are also
welcome but not necessary. In many cases, we should have some idea of the
scope of the problems involved.
Beam suggestions should be within the relevant facility
parameters/capabilities listed below.
RA6. HRIBF Experiments,
January through July 2009 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||